Description |
Pass |
Fail |
Remarks |
|
Documentation |
|
|
|
|
1.
AS BUILT drawings and component operating
instructions provided. |
|
|
|
|
Exterior QC: |
|
|
|
|
2.
All door mounted apparatus and associated labels
installed. |
|
|
|
|
3.
Exterior attachments laid out as designed. |
|
|
|
|
Interior QC |
|
|
|
|
4.
EVERY component is labeled (tagged) to match the
ladder diagram. |
|
|
|
|
5.
All wiring neat, properly bundled, in wireways
and/or wrapped. |
|
|
|
|
6.
All wiring connections to components are secure
(pull test). Check for pinched insulators, loose
terminal screws, loose connections, etc. |
|
|
|
|
7.
Check fuses and circuit breakers for proper
sizing according to dwg. |
|
|
|
|
8.
All terminal block points with wire #s are wired
with % spare. |
|
|
|
|
9.
All wiring labeled on both ends with Grafoplast
or equal. |
|
|
|
|
10.
Panel UL certified if required |
|
|
|
|
Functional Tests |
|
|
|
|
11.
Transformer input / output voltage as specified. |
|
|
|
|
12.
All components configured
Controllers, instruments, timers, VFDs, recorders, PID
functions, etc. |
|
|
|
|
13.
Install jumpers as needed to simulate proper
input/output signals and test ALL interlocks and
circuits for proper functional operation. |
|
|
|
|
14.
Install analog meter (4-20mA) as needed to
measure analog outputs resulting control panel
operational functions as needed. |
|
|
|
|
15.
Install analog generator (4-20mA) to simulate
analog inputs and resulting control panel operational
functions as needed. |
|
|
|
|
16.
Set or verify each motor OL setting to FLA data
found on drawing |
|
|
|
|
17.
Trip each motor OL and verify door mounted light
operation. |
|
|
|
|
18.
Trip each motor OL and verify output signal
operation. |
|
|
|
|
19.
Operate all selector switches and verify interior
component operation.
ie: Motor starters, VFDs, control relays, etc. |
|
|
|
|
20.
Operate all selector switches and verify pilot
light operation.
Verify proper operation under normal and OL tripped
conditions. |
|
|
|
|
21.
Simulate all system fault signals and verify
proper operational results, if any. Alarms, relays,
inputs/outputs, horn, dialer, HMI banners, etc. |
|
|
|